Car park surfacing contractors
New car park construction and full resurfacing, including the drainage, kerbing and line marking that make the finished area work.
In short
Car park surfacing covers the whole build: excavation and sub-base, drainage, kerbs and edgings, binder and surface courses, then line marking and signage. Quoting only the black surface is what makes two prices look different when they are not comparable.
On this page
What a full car park scheme includes · Layout: getting more from the same area · Drainage · Programme and disruption
A car park is not a surfacing job with some extras bolted on. It is a drainage and layout job with a surface on top. Water has to get off it, vehicles have to circulate without conflict, and the bays have to work for the people using them.
We build and resurface car parks for retail, offices, industrial estates, schools, hotels and public buildings, and we price the whole thing rather than the easy part.
What a full car park scheme includes
- Site survey, levels and falls
- Excavation or planing, and removal of arisings
- Sub-base construction and compaction
- Drainage: gullies, linear channels, connections or soakaways
- Kerbs, edgings and islands
- Binder and surface courses, machine-laid where access allows
- Line marking, bay numbering, disabled and EV bays, directional arrows
- Bollards, wheel stops and signage where required
Layout: getting more from the same area
Resurfacing is the cheapest moment to change a layout, because the lines are going back on anyway. Things worth reviewing before we start:
- Bay dimensions — older car parks were often laid out for smaller cars
- Circulation and one-way flow, particularly where deliveries share the space with visitors
- Accessible bays: number, position relative to the entrance, and hatching
- EV charging bays and the ducting to serve them — far cheaper to install before the surface goes down
- Pedestrian routes from the parking area to the door
Drainage
Standing water is the single most common cause of premature car park failure. It works into the surface, freezes, and lifts the material apart. On a resurfacing job we check where water currently sits and why, then correct the falls, add or reset gullies and channels, and make sure the new levels shed water rather than trapping it against a building or kerb line.
Where mains connection is not available or permitted, soakaways and permeable build-ups are the usual alternatives.
Programme and disruption
Most car parks are phased so the site keeps functioning. A rough guide for a straightforward resurfacing job with reasonable access:
| Area | Typical duration, site closed | Typical duration, phased |
|---|---|---|
| Up to 500m² | 2–3 days | 4–5 days |
| 500–1,500m² | 3–5 days | 1–2 weeks |
| 1,500m²+ | By programme | By programme |
Add time for drainage and kerbing works, and for line marking, which needs the surface to be clean and dry.
How projects run
The same five stages on every job, scaled to the site.
Site survey
We measure the area, assess the existing surface and ground conditions, and check access for plant and deliveries.
Specification and quote
A written quote setting out the build-up, depths, materials, drainage, edgings and what is excluded.
Preparation
Planing or excavation, removal of arisings, sub-base laying and compaction, plus any drainage and kerbing.
Laying
Binder and surface courses laid and rolled to the specified depth, with joints and levels set out against falls.
Handover
Line marking where required, site cleared, and written guidance on when the surface can take traffic.
Questions we get asked
Anything not covered here, call 0208 050 7207.
It depends far more on preparation and drainage than on the surface itself. A straightforward overlay on a sound base is at the cheap end; a full rebuild with new drainage, kerbs and lining is several times that per square metre. We give a fixed price after a site survey, with the build-up stated so you can compare quotes properly.
Yes, and most are done that way. We agree the phases with you before starting so you know which areas are out of use and when.
We can form and mark the bays and lay ducting while the surface is up, which is much cheaper than retrofitting. The electrical installation itself would be by your contractor. [Confirm scope before publishing]
Line marking normally goes down once the surface has cooled and is clean and dry — often the following day. Thermoplastic and paint have different requirements and we will tell you which we are using.
[Confirm whether Cooper Jackson works on multi-storey and deck waterproofing before publishing this answer]